ARTZ 371: Advance Screen / WEEKLY SCHEDULE Spring 2025
WK 1/
Jan 20- MLK Holiday- No Classes
Jan 22- Introduction to course, materials & Introduce Project 1/Self Portrait show samples. Overview of Printmaking. Read Basics of Screenprinting handout.
WK 2/
Jan 27- Demo basics of Screenprinting. Short quiz
Jan 29- Show separation samples, hand drawing/lining up, acrylic & brush.
WK 3/
Feb 3-Discussion on papers/ Demo: dyeing/spray paint/bubble paper.
Feb 5-Print Session
WK 4/
Feb 10- Project 1 due/Critique
Feb 12- Intro Project 2 / Ppt: Protest or Propaganda & examples. Demo: Halftones, CMYK, Posterizations, Pin registration & using a vacuum frame.
Bring T-shirts next Wednesday if you want one printed. (this is optional)
WK 5/
Feb 17- Holiday-No Classes
Feb 19- Optional T-shirt printing day
WK 6/
Feb 24- Visiting Artist / David Miles Lusk
Feb 26- Visiting Artist / David Miles Lusk
WK 7/
Mar 3- Introduce Project 3/Indept project
Mar 5 Project 2 due/Critique
WK 8/
Mar 10-
Mar 12-Introduce Project 4 / Image/text
WK 9/
Mar 17- Spring Break
Mar 19- Spring Break
WK 10/
Mar 24-Visiting Artist / Duane Slick
Mar 26-Visiting Artist / Duane Slick
WK 11/
Mar 31- Project 3 due/critique
April 2- Intro Final Portfolio / Select theme
WK 12/
April 7
April 9
WK 13/
April 14- Project 4 due/Critique
April 16
WK 14/
April 21
April 23
WK 15/
April 28- Print Session
April 30- Final Portfolio due & Final mandatory class clean up. Return all materials, squeegees, registration pins.
The Print Studio will be closed to printing after our clean up.
WK 16/ FINALS WEEK
May 5-9 We will not be meeting, use this time to clear out your flat files, lockers and any prints left in the drying racks and remove your screens.
All lockers & flat files must be cleaned out no later than Sunday of Finals week. The print studio will be locked starting Monday. All items left behind will be tossed.
Jan 20- MLK Holiday- No Classes
Jan 22- Introduction to course, materials & Introduce Project 1/Self Portrait show samples. Overview of Printmaking. Read Basics of Screenprinting handout.
WK 2/
Jan 27- Demo basics of Screenprinting. Short quiz
Jan 29- Show separation samples, hand drawing/lining up, acrylic & brush.
WK 3/
Feb 3-Discussion on papers/ Demo: dyeing/spray paint/bubble paper.
Feb 5-Print Session
WK 4/
Feb 10- Project 1 due/Critique
Feb 12- Intro Project 2 / Ppt: Protest or Propaganda & examples. Demo: Halftones, CMYK, Posterizations, Pin registration & using a vacuum frame.
Bring T-shirts next Wednesday if you want one printed. (this is optional)
WK 5/
Feb 17- Holiday-No Classes
Feb 19- Optional T-shirt printing day
WK 6/
Feb 24- Visiting Artist / David Miles Lusk
Feb 26- Visiting Artist / David Miles Lusk
WK 7/
Mar 3- Introduce Project 3/Indept project
Mar 5 Project 2 due/Critique
WK 8/
Mar 10-
Mar 12-Introduce Project 4 / Image/text
WK 9/
Mar 17- Spring Break
Mar 19- Spring Break
WK 10/
Mar 24-Visiting Artist / Duane Slick
Mar 26-Visiting Artist / Duane Slick
WK 11/
Mar 31- Project 3 due/critique
April 2- Intro Final Portfolio / Select theme
WK 12/
April 7
April 9
WK 13/
April 14- Project 4 due/Critique
April 16
WK 14/
April 21
April 23
WK 15/
April 28- Print Session
April 30- Final Portfolio due & Final mandatory class clean up. Return all materials, squeegees, registration pins.
The Print Studio will be closed to printing after our clean up.
WK 16/ FINALS WEEK
May 5-9 We will not be meeting, use this time to clear out your flat files, lockers and any prints left in the drying racks and remove your screens.
All lockers & flat files must be cleaned out no later than Sunday of Finals week. The print studio will be locked starting Monday. All items left behind will be tossed.